The Bay Avenue Offramp Will Reopen Before the Construction Leaves Soquel

"We just want it to be over," Joe Ortiz, co-owner of Gayle's Bakery & Rosticceria, told the Santa Cruz Sentinel in early August, the day after the southbound Highway 1 offramp at Bay Avenue closed. Three months on, the closure is still in place. Its end is now close enough to plan around, but it isn't fixed.

The reopening will end one detour. The work at the Bay Avenue and Porter Street interchange will go on. The ramp closure is one step in a multiyear highway project that will keep crews near Soquel's main exit into 2027, and it includes a northbound closure that hasn't been scheduled yet.

The Four-Month Clock Started on August 2

The closure began overnight on August 2 at 10 p.m., according to the Caltrans District 5 announcement. Crews are rebuilding the ramp to fit the new bus-on-shoulder lanes. Both Caltrans and the Santa Cruz County Regional Transportation Commission gave the same length for the closure, "approximately four months."

Here is how that estimate stands as of this week:

Item What the agencies have published
Closure start August 2, 10 p.m.
Stated length Approximately four months
Where four months lands Around the first days of December
Latest RTC weekly update, October 14 Same "approximately four months" wording, no new date
Earlier local reporting The 831 described the closure as running "through November"

As of the RTC's construction updates page, no one has announced a reopening day. The best working assumption is late November or early December. A ramp rebuilt for a new kind of highway lane could also open a little before or after that.

Until it reopens, southbound drivers heading for Bay Avenue or Porter Street get off at Park Avenue. From there, the detour runs along Park Avenue to Soquel Drive and then follows signs back to the Porter Street and Bay Avenue area. The detour signs are the most reliable guide for the turns.

A Second Ramp Closure From the Spring

The Bay Avenue offramp isn't the only ramp in this stretch with a long closure. On April 19, crews closed the southbound Highway 1 onramp at Park Avenue for about six months. The RTC said that section needed a full structural replacement of the roadway. Six months from April 19 is mid-October. The RTC's October 14 update still listed that closure and didn't say whether it had reopened. Its posted detours send drivers south on Soquel Drive or McGregor Drive to the State Park Drive onramp.

For anyone who lives between Porter Street and Park Avenue, these two closures overlap. One changes how you get off the highway heading home, and the other changes how you get on heading south. Both send traffic onto Soquel Drive.

Overnight work has added to it. The RTC's October 14 update described overnight lane closures between the Park Avenue Bridge, the Mar Vista overcrossing and the Capitola Bridge for paving on the widened outside lanes. The update warned nearby residents to expect loud noise. Those closures began in late September and were expected to last about two more weeks from that update. That schedule would put the end of the paving phase around the end of October.

Why Reopening Day Won't Mean the Work Is Done

The Bay Avenue ramp belongs to Phase II of the Highway 1 Auxiliary Lanes and Bus-on-Shoulder project. Phase II is a $78 million segment from Bay Avenue and Porter Street to State Park Drive. It broke ground in April 2024, and Granite Construction of Watsonville is the contractor. The phase also includes a new bicycle and pedestrian overcrossing at Mar Vista Drive and a replacement of the Capitola Avenue overcrossing.

The finish date for Phase II depends on which page you read:

  • The RTC's construction updates page says Phase II is expected to be finished in 2026.
  • The RTC's project page lists construction as running from spring 2024 to 2027.
  • In August, RTC Executive Director Sarah Christensen told the Sentinel the phase was expected to wrap up in late spring or early summer 2027. She also said Phase III would begin in late 2027.

The most specific and most recent statement on the record is Christensen's 2027 estimate. Even with the southbound ramp back in service, crews will likely still be working along this corridor through next spring.

The same Sentinel report also said a northbound Bay Avenue offramp closure is planned, but not at the same time as the southbound one. No schedule has been published. For anyone who comes home on northbound Highway 1 from Santa Cruz and exits at Porter Street, that is the date to watch. The RTC says it posts construction updates weekly.

The Corner Right Next to the Exit

The businesses hit hardest by the closure sit at Holiday Corners, a few hundred feet from the ramp. Holiday Corners LLC owns the properties where Beer Thirty, Carpo's Restaurant, Buzzo Pizza and Sunnyside Produce operate side by side, according to manager Erik Barbic in the Sentinel's August report.

Beer Thirty co-owner Kym DeWitt explained to the Sentinel why the ramp matters so much to her business. "Bay Avenue is our direct exit and if people can't get off the exit, they're likely to go to a different establishment," she said. She added that the shop's revenue rises about 60% in summer. The traffic she described comes from drivers passing through. The closure doesn't change how people already in Soquel reach the corner. The only movement it blocks is southbound drivers getting off at Bay Avenue. From Soquel Village, Main Street or the neighborhoods off Porter Street, the trip is the same as it was in July.

Carpo's co-owners told the Sentinel that the restaurant stayed open and accessible, and they asked locals to support it through the fall. Here is what's at the corner:

  • Carpo's Restaurant, 2400 Porter St. has served Soquel since 1981. It's known for American classics, burgers, local produce and a large salad bar. Good Times marked its 40th anniversary by highlighting the Pacific rock-cod fish and chips and the homemade fruit pies, especially olallieberry. Its Visit Santa Cruz County listing, last updated May 14, 2026, shows hours of 11:30 a.m. to 8:30 p.m. daily.
  • Buzzo Wood-Fired Pizza, 2510 S. Main St. makes wood-fired pizza, and Good Times described the menu as inventive and built around seasonal ingredients. Its Visit Santa Cruz County listing, updated April 27, 2026, shows dinner from 5 to 8:30 p.m. on Sunday and Tuesday through Thursday, and 5 to 9 p.m. on Friday and Saturday. It's closed Mondays, and lunch is to-go only, Friday through Sunday.
  • Beer Thirty Bottle Shop and Pour House, 2504 S. Main St. is a craft beer bottle shop with a pour house next door to the other two.
  • Sunnyside Produce rounds out the Holiday Corners tenants that Barbic named.

Business hours change with the seasons, so check each listing before a weeknight visit.

About half a mile toward the coast on Bay Avenue, Gayle's offers a contrast. In early August, Ortiz said it was too early to know whether the closure would affect the bakery, but business hadn't slowed so far. Distance from the ramp seems to have mattered. The businesses right at the exit had the most reason for concern.

Why the Work Happened in Summer

The timing of the closure frustrated some of the businesses. The RTC gave its reason. Christensen told the Sentinel that dry weather makes it easier to do critical construction such as the large retaining walls this closure allows. She called the closure "short-term pain for the long-term gain." Barbic said the tenants support the highway work and mainly wished they'd had more notice so they could plan supplies and staffing.

The finished project will add something new to Soquel's stretch of highway. The bus-on-shoulder system, which project leaders describe as the first of its kind on a California highway, will let Santa Cruz Metro buses use the shoulder during peak traffic. Phase I, from 41st Avenue to Soquel Drive, opened in spring 2025 along with the Chanticleer bicycle and pedestrian overcrossing.

Before December, put two pages in your bookmarks. The RTC construction updates page is where a reopening date or the northbound closure schedule is likely to show up first. Caltrans District 5 posts road updates on its social channels, which are linked from its closure announcement.

At Brett Gotcher, I follow changes like this one because a ramp closure, a detour or a long construction window changes how a part of Soquel works day to day. If you're thinking about how the Porter Street and Bay Avenue area will settle once the highway work wraps up, I'm glad to talk it through. Let's Connect.

Work with Brett Gotcher

Whether buying your first home, selling a property, or planning your next move, Brett provides personalized guidance and local expertise to help you move confidently.

Follow Me on Instagram