Ivory stucco home with a clay-tile roof, recessed arched oak entry, and a brick-edged garden beside a concrete walk.

Watsonville Ramsay Park Reopening and City Plaza Renovation

Watsonville's two best-known public spaces are going through rebuilds on opposite timelines. Ramsay Park has been closed since 2024 and is expected to be finished in November. City Plaza is near the end of its first, smaller phase, and the larger second phase won't start until spring 2027. In the meantime, several things that normally happen on the Plaza are happening elsewhere. That includes the downtown Día de Muertos open streets, and community building of the Plaza's new stage art is scheduled at a studio across town.

Ramsay Park's Reopening Has a Month, Not a Date

The Santa Cruz Sentinel reported on September 9, 2026 that the Ramsay Park remodel was expected to be finished in November. Nick Calubaquib, Watsonville's deputy city manager and director of parks and recreation, told the council the park would open again "in just less than a couple of months." That report gave a month but no specific reopening day. A June 2026 city parks report mentions keepsakes bought for a Ramsay Park Renaissance ribbon-cutting.

The schedule slipped. At the May 2024 groundbreaking, the Sentinel reported about 15 months of construction by Robert A. Bothman Inc., with completion expected in summer 2025. November 2026 makes it about two and a half years.

The council is already planning for daily use. Its September Measure Q allocation set aside $101,060 this fiscal year for two full-time and two seasonal maintenance workers at Ramsay. Calubaquib said the parks maintenance staff had shrunk through attrition while the park was closed.

What the $33 Million Was Planned to Buy

Ramsay opened in 1973 and was named for Dr. Will Ramsay, a former mayor and longtime local veterinarian. Its last major overhaul was in 1991, when the playgrounds, ballfields, amphitheater and tennis courts that most adults remember were built. The Renaissance project was funded by the city, Measure R, American Rescue Plan Act money and state grants secured by Assembly Speaker Robert Rivas. These are the features described at the groundbreaking:

  • A multiuse field for both soccer and softball. Lookout Santa Cruz described this in 2025 as converting the softball field.
  • A renovated Sotomayor Field with hillside spectator seating
  • A dog park with separate areas for large and small dogs
  • A Nature Center with a picnic area, an accessible trail and a concrete amphitheater
  • An inclusive playground with a sensory play area, cargo nets, and swings and see-saws built for several children at once

That list describes the 2024 plans. The city hasn't yet published which features will be ready on opening day. One familiar piece is staying. Mayor Vanessa Quiroz-Carter said at the groundbreaking that the large metal slide would stay in place. The family center, skate park and pump track were already built before this project began.

The Plaza's Larger Closure Is Still Ahead

KSBW reported in May that the city had begun a $7 million revitalization of City Plaza, a project six years in the making. Phase one covers the two historic features, the gazebo and the fountain. The plan is to retrofit both while keeping how they look. The gazebo has been closed to the public since the 1989 Loma Prieta earthquake.

Phase two is the bigger change. It brings new landscaping, ADA-compliant walkways, picnic tables and a permanent stage. In May, KSBW reported that the park would close temporarily once phase two began "later this fall." That timing has moved. In the September Sentinel report, Calubaquib said phase one was nearing completion and that phase two would go out to bid in January 2027, with construction expected to start in April 2027.

He also said the city has been "pretty far short of being able to fully fund that project." The council added $803,252 in Measure Q money to the Plaza, which included $40,000 originally proposed for a Pinto Lake water quality study.

If both schedules hold, Ramsay reopens a few months before the Plaza's biggest disruption starts.

The Plaza's New Art Starts Across Town

The permanent stage will have mosaic art chosen by the community. Earlier this year the city asked for public input on the stage designs. Local artist Kathleen Crocetti was originally awarded the project and stepped aside. She explained why to KSBW:

"It was originally awarded to me personally. And I said to the city, you know, that there's enough of me here in the plaza. Let's open this up to other artists."

Crocetti is now making four interactive murals, one for each corner of the Plaza, under the title "Pageantry and Performance." Each represents one of the cultures that make up the Watsonville community.

The stage skirt, the mosaic band around the base of the stage, is a project of Community Arts & Empowerment, which scheduled community mosaic-building for it at its Muzzio Mosaic Arts Center from late summer through fall 2026, with completion targeted for summer 2027. The project is funded by the City of Watsonville. Its most recent posted schedule, from September, listed adult community sessions on Wednesdays from 3 to 7:30 p.m. and youth sessions Monday through Thursday over the same hours. Check the organization's site for current hours before you go. The same September update said a Mexican Bench for the Plaza was "coming along."

There's also new public art outside downtown. In early September, the City Council accepted three donated sculptures for the Clifford Avenue roundabout. An anonymous Watsonville resident is paying for them, Melissa Marzan designed the images, and work has begun.

Día de Muertos Moves a Few Blocks

The Plaza changes show up most clearly in this year's Día de Muertos calendar. Growing Greatness hosts Calles Libres, Watsonville's open streets event. The city's 2025 calendar placed last year's November edition at City Plaza Park, at Main and Peck streets. This year's edition is on Sunday, November 1, from noon to 4 p.m. at Callaghan Park on Brennan Street. Visit Santa Cruz County's listing still calls it "Watsonville Plaza: Day of the Dead Open Streets" and gives the address as 225 Sudden Street. It's free, and the listing describes car-free streets for biking, walking and skating, live music and dance, family art activities, yoga and Zumba, Día de los Muertos traditions and local vendors.

The rest of the season is spread along Main Street and out to the fairgrounds:

  1. Thursday, October 29, 5:30 to 7:30 p.m. The Watsonville Main Library hosts free, all-ages Día de Los Muertos Festivities at 275 Main Street, Suite 100, with an art display, lotería, a scavenger hunt, a photo spot and pan dulce.
  2. Thursday, October 29, 5 to 7 p.m. Pajaro Valley Arts holds an alebrije-painting workshop. Registration is $65.
  3. October 27 into early December. Pajaro Valley Arts' annual Mi Casa es Tu Casa exhibition, "Paths of Remembrance / Caminos de Recuerdo," curated by Nessa Ledesma, is at the Porter Building, 280 Main Street. The gallery's own pages give two closing dates, December 5 and December 7.
  4. Sunday, November 1, noon to 3 p.m. The Mi Casa es Tu Casa community celebration at Pajaro Valley Arts overlaps with Calles Libres.
  5. Saturday, November 7, 1 to 3 p.m. Creative-writing workshop at Pajaro Valley Arts, $20. Saturday, November 14, 1 to 3 p.m. Artist talk with Josie Lepe.
  6. November 13 and 14. The Goat Hill Fair antique-and-vintage fair returns to the Santa Cruz County Fairgrounds, 2601 East Lake Avenue. The Agricultural History Project Center & Museum at the same address is open every second Saturday from 11 a.m. to 3 p.m., and November 14 is one of those Saturdays.

The Next Few Dates to Watch

Three updates will shape Watsonville's park calendar over the coming months. The first is the official Ramsay Park reopening date, expected sometime in November. Then the Plaza's phase-two bid goes out in January, and construction is expected to start in April. The mosaic for the new stage is on its own schedule, with community building at the Muzzio planned through this fall and a summer 2027 completion target.

Brett Gotcher follows projects like Ramsay Park and the Plaza because they change how people use a town, and he's happy to talk through what the next year of park work means for your part of Watsonville. Let's Connect.